What we renovate
Kitchen renovations
Full kitchen strip-out and rebuild — new cabinetry, benchtops (stone, timber, laminate), appliances, plumbing, electrical, tiling, splashbacks, and flooring. We coordinate the cabinet maker, stone fabricator, plumber, electrician, and tiler so you deal with one builder, not five tradespeople.
Typical scope: 3m x 4m kitchen, mid-range finishes, $35,000-$55,000 + GST. High-end stone, integrated appliances, and custom joinery can push this to $70,000-$90,000 + GST.
Timeline: 6-8 weeks from contract signing to practical completion. 2-3 weeks on-site (demo, rough-ins, install, finishing).
Bathroom renovations
Full bathroom strip-out and rebuild — new fixtures (shower, bath, vanity, toilet), tiling (walls and floor), waterproofing, plumbing, electrical, ventilation, and accessibility modifications (grab rails, level-threshold showers, wider doors).
Typical scope: Standard 2m x 2.5m bathroom, mid-range tiles and fixtures, $25,000-$40,000 + GST. Ensuite or powder room: $18,000-$28,000 + GST. Accessibility modifications (NDIS-compliant): add $8,000-$15,000 depending on scope.
Timeline: 4-6 weeks from contract signing to practical completion. 2-3 weeks on-site.
Full-house renovations
Complete internal reconfiguration — knock out walls, open up living areas, new kitchen and bathrooms, new flooring, repaint, new lighting and electrical, replumb, re-roof (if needed), and external cladding or render.
Typical scope: 3-bedroom fibro or brick cottage, full internal renovation (kitchen, bathroom, living, flooring, paint), $120,000-$200,000 + GST depending on finishes and structural changes. Adding a second storey or significant extension: see Extensions.
Timeline: 3-6 months from contract signing to practical completion. You may need to move out for 6-12 weeks during heavy demolition and rough-in work.
Cosmetic renovations
Paint, new flooring (timber, hybrid, tile), new light fixtures, new doors and hardware, kitchen benchtop replacement (no cabinet change), bathroom vanity and mirror upgrade — no structural work, no plumbing relocation, no electrical panel upgrade.
Typical scope: 3-bedroom house, repaint interior, new hybrid flooring in living areas, new benchtop and splashback in kitchen, $30,000-$50,000 + GST.
Timeline: 3-5 weeks from contract signing to practical completion. You can usually stay in the house the whole time.